Skip to content

Altech Batteries Limited

ASX | ATC Battery Technology
17 Apr 2024

Altech Batteries Limited Uploaded a Corporate Update
April 17, 2024

Altech Batteries Provides Details on Share Purchase Plan Prospectus

Download Content in Link Below for Additional Details

17 Apr 2024

Altech Batteries Limited Uploaded a Corporate Update
April 17, 2024

Altech Batteries Provides Additional Details on Share Purchase Plan

Download Content in Link Below for Additional Details

17 Apr 2024

Altech Batteries Limited Uploaded a News Release
April 17, 2024

Altech Batteries – Launch of Share Purchase Plan

Release Highlights:

  • Altech is delighted to announce the opportunity for eligible shareholders to participate in an equity raising via the launch of its Share Purchase Plan (SPP)
    to raise up to AUD 5M.
  • The SPP follows the excellent Definitive Feasibility Study (DFS) for the CERENERGY® project which included an NPV(9) of EUR 169M and free cash flow of EUR 48M p.a.
  • The shares issued pursuant to the SPP will be at an issue price of AUD 0.065 per share with one free attaching option for every two shares acquired. The options will be exercisable at AUD 0.08 per share and will expire on 30 April 2026.

22 Mar 2024

Altech Batteries Limited Uploaded a Corporate Update
March 22, 2024

Altech CEO Iggy Tan’s Interview on the CERENERGY Definitive Feasibility Study

Chief Executive Officer Iggy Tan comments on Altech’s recently released CERENERGY DFS. Please download details and a link to the recording below.

19 Mar 2024

Altech Batteries Limited Uploaded a News Release
March 19, 2024

Altech Announces Excellent Definitive Feasibility Study for 120 MWh First Production Line CERENERGY® Battery Project

DFS Highlights:

  • Highly positive Definitive Feasibility Study (DFS) – 120 GridPacks (1MWh) pa
  • Capital cost estimated at €156 million with excellent project economics
  • Pre-tax Net Present Value (NPV9) of €169 million
  • Attractive Internal Rate of Return (IRR) of 19%
  • Steady state payback period is 3.7 years, with Annual Revenue of €106 million per annum
  • EBITDA of €51 million or margin of around 47%
  • Altech Board Decision to Proceed to Funding Phase
  • Low lifetime levelised cost of storage €0.06/kWh vs lithium-ion batteries at €0.149/kWh
  • Grid energy storage market projected to grow by 28% CAGR
  • Grant funding applications underway
  • Equity and mezzanine financing discussions in progress
  • Offtake for 5 years production in progress
13 Mar 2024

Altech Batteries Limited Uploaded a Earnings Report
March 13, 2024

Altech Batteries Publishes Half-Year Report

Altech Batteries recently published its Interim Financial Report for the Half-Year ended 31 December 2023, which can be downloaded here.

6 Feb 2024

Altech Batteries Limited Uploaded a News Release
February 6, 2024

Altech Announces Excellent Progress on ABS60 60kWh Cerenergy Battery Prototypes

Release Highlights:

  • Excellent progress with two 60 kWh battery pack prototypes
  • Pilot plant re-design at Fraunhofer IKTS Hermsdorf for prototype manufacture
  • All prototype materials have been procured from suppliers
  • Ceramic tube manufacture is 50% complete
  • Cell assembly progressing well with more than half completed
  • Low reject and defect rates experienced
  • Two battery vacuum casings delivered and undergoing heat loss testing
  • Finalization of prototypes will be mid 2024
11 Jan 2024

Altech Batteries Limited Uploaded a News Release
January 11, 2024

Silumina Anodes Battery Materials Project DFS – Additional Information

Altech Batteries Limited provides additional information in relation to the announcement on 21 December 2023 of the Definitive Feasibility Study (DFS) for an 8,000tpa (120 GWh) alumina-coated metallurgical silicon plant envisaged for Saxony, Germany.

8 Jan 2024

Altech Batteries Limited Uploaded a News Release
January 8, 2024

Altech – Funds received for sale of 25% of Altech Industries Germany

Highlights:

  • Altech Batteries Limited (ASX: ATC, FRA: A3Y) successfully sold a 25% stake in Altech Industries Germany GmbH (AIG) to Altech Advanced Materials AG (AAM).
  • Altech received the final €1,583,333 instalment from AAM, completing the €5.0 million deal, structured with an Initial Cash Consideration of €250,000 and Deferred Consideration in three equal parts.
21 Dec 2023

Altech Batteries Limited Uploaded a News Release
December 21, 2023

Altech Announces Outstanding Definitive Feasibility Study for Silumina Anodes Battery Materials Projects

Definitive Feasibility Study Highlights:

  • Highly positive Definitive Feasibility Study for the 8,000tpa Silumina AnodesTM project
  • 8,000 tpa alumina-coated metallurgical silicon only
  • Customers to blend coated silicon (10%) with their uncoated graphite source
  • Means expansion from 15 gigawatt-hours (GWh) to 120 gigawatt-hours (GWh)
  • Increase of battery energy density by at least 30%
  • Capital cost estimated at €112 million with outstanding economics
  • Pre-tax Net Present Value (NPV10) of €684 million
  • Attractive Internal Rate of Return (IRR) of 34%
  • Payback period is 2.4 years
  • Forecast 18% CAGR growth of silicon in battery anodes till 2035
  • Green accredited project using renewable energy
  • Pilot plant construction in final stages for product qualification
  • NDAs executed with two German automakers, two US automakers, one US battery materials supply company and one European battery maker

Industries

  • Battery Technology
    • Battery Material Technology
  • Sodium

Altech Chemicals Ltd is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS (“IKTS”) to commercialise the revolutionary CERENERGY® Sodium Alumina Solid State (SAS) Battery.

CERENERGY® batteries are the game-changing alternative to lithium-ion batteries. CERENERGY® batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.

The joint venture is commercialising its CERENERGY® battery, with plans to construct a 100Mwh production facility on Altech’s land in Saxony, Germany. The facility intends to produce 10,000 10Kwh CERENERGY® battery modules per annum to provide grid storage solutions to the market.